Dadhapara-Belha-Dagori & Nipania-Bhatapara-Hathbandh
Construction of electricfied 4th line railway BG line between Dadhapara-Belha-Dagori & Nipania-Bhatapara-Hathbandh stations, in the state of chhattisgarh in South East Central Railway on EPC mode
Project under Concerns : SECR / BILASPUR / CON-I
Location : Dadhapara-Dagori & Nipania-Bhatapara-Hathbandh station ,South East Central Railway Bilaspur-495004
Project Start Date : 25-May-2024
Expected Completion Date: 11-November-2026
Project Value: Rs. 1,98,00,76,740.48