Rajnandgaon-Dongargarh & Bhilai-Durg Link Block stations
Construction of electricfied 4th line railway BG line between Rajnandgaon-Dongargarh & Bhilai-Durg Link Block stations, in the state of chhattisgarh in South East Central Railway on EPC mode
Project under Concerns : SECR / BILASPUR / CON-II
Location : Rajnandgaon-Dongargarh & Bhilai-Durg Link Block stations ,South East Central Railway Bilaspur-495004
Project Start Date : 11-Jun-2024
Expected Completion Date: 28-Nov-2026
Project Value: Rs. 1,50,01,21,286.66